Supply Installation, testing and commissioning of 220kV HGCP substation & 220kV OHTL from BABG
Project Info
Project code:
P-221
Client :
TAQA
Date :
2024
Location :
Habshan, Abu Dhabi
Scope of work :
Installation of Board piles ( 800, 1000 & 1200 mm dia full length casing ) works and Pile Testing
KON delivered board piling works in Habshan for TAQA 220kV HGCP substation & 220kV OHTL from BABG project, installing 800 mm, 1000 mm, and 1200 mm diameter piles with full-length casing to maintain ground stability. Pile testing was also performed to verify foundation performance, with the works executed through clear planning, strong quality control, and safe site practices.